October, 2009 |
 |
 |
 |
 Looking Towards Hughes Ave. Fence |
November, 2009 |
 Scrapped Rock Work Completed |
 Looking towards Belmont Avenue |
December, 2009 |
 Fence on Belmont not Completed yet |
 Along North Side by Hughes Gate |
January, 2010 |
 |
 |
February, 2010 |
 Removal Along Neighboring Building |
 Line Drill Rig and Operator |
March, 2010 |
 More than 75% across wall to Belmont Side |
 Channel Drilling at Center of Site |
April, 2010 |
 Beneath 2 story building along south |
 New fence along north side |
 |
 Diagonal view across site looking north |
May, 2010 |
 Section along south opened up |
 Orange Markers for layout of foundation footing |
 Beginning of footing forms at center of site |
 Concrete poured, installing dowels and leveling pads at center of site |
 Rebar work where waterproofing has been installed |
 Moving fresh backfill |
June, 2010 |
 Rebar at bottom of elevator & sump pits |
 Masons building mock-up of wall assembly |
 Looking at north walls and insulation installed |
 Backfill and compaction completed behind foundation wall |
July, 2010 |
 Pouring concrete into elevator shaft |
 Concrete formwork in progress |
 Rough Belmont Side foundation wall |
 |
September, 2010 |
 Masonry work all complete belmont side |
 Temporary lighting in place at 5 story side |
 Ramp from belmotn to 5 story area here at 1st fl |
|
November, 2010 |
 |
 Masons completing block work at north-5th fl |
 Plumbing roughin |
 Concrete lintels set all around |
December, 2010 |
 Brick facade going up |
 Plumbing installed |
 From Belmont Avenue |
|
February, 2011 |
 Courtyard with scaffolding |
 Roofers Progress |
 Stairs A |
 Stucco progress roof |
 |
 |
May, 2011 |
 Courtyard Progress |
 Title work |
 Tapers at work |
 Divider pieces installed at windows |
 Title work 2 |
|
June, 2011 |
 Laundy room |
 Foyer |
 Courtyard subflooring installed |
 Shower |
 Belmont service door |
|
October, 2011 |
 Hughes Avenue elevation |
 Security desk |
 2nd fl Balcony & Planters |
|
February, 2012 |
 Hughes storefront replaced |
 Mailroom countertop installed |
|